Kansal Reviews Electrification Of Udhampur-Baramulla Rail Link

Date:

Straight Line News Network

SRINAGAR: Principal Secretary, Power Development Department, Rohit Kansal, chaired a meeting to review progress on electrification of Udhampur-Srinagar-Baramulla Rail Link, USBRL.

Principal Secretary had an elaborated discussion on several vital issues related to the project like laying of 132 KV transmission line between Katra-Reasi, Ramban-Sangaldan, Budgam Grid Sub-Station-Railway TSS, Mir Bazar-Qazigund and Delina-Baramulla besides land acquisition and department clearances were also deliberated upon.

Rohit Kansal was apprised that although the electrification project was hindered by Covid pandemic and by unexpected geological surprises in Katra-Reasi line yet much of it has been completed.

Principal Secretary said that the project is of national significance and all the bottlenecks and hurdles need to be removed with inter agency coordination ensuring project completion within stipulated time. ‘Timely completion of the prestigious railway project by 2022 is our only priority’, he maintained.

It is pertinent to mention that the works from Reasi to Banihal are being executed by Konkan Railways Corporation Limited, while the rest are being taken care of by IRCON Limited.

Principal Secretary asked the executing agencies and the Power Development Department for resolution of the most pressing issues including payment to contractors. He also set deadlines for completion of the project which were amicably accepted by all stakeholders present at the meeting.

Rohit Kansal was apprised that although the electrification project was hindered by Covid pandemic and by unexpected geological surprises in Katra-Reasi line yet much of it has been completed.

Principal Secretary said that the project is of national significance and all the bottlenecks and hurdles need to be removed with inter agency coordination ensuring project completion within stipulated time. ‘Timely completion of the prestigious railway project by 2022 is our only priority’, he maintained.

It is pertinent to mention that the works from Reasi to Banihal are being executed by Konkan Railways Corporation Limited, while the rest are being taken care of by IRCON Limited.

Principal Secretary asked the executing agencies and the Power Development Department for resolution of the most pressing issues including payment to contractors. He also set deadlines for completion of the project which were amicably accepted by all stakeholders present at the meeting.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Share post:

Subscribe

spot_imgspot_img

Popular

More like this
Related

Now BJP won’t have courage to allow polls in J&K, says Omar after Karnataka election results

SRINAGAR: Former Chief Minister Omar Abdullah Saturday said the...

Last date for applying online ATD-2023 extended till May 15

SRINAGAR: School Education Department has xtended last date of...

J&K | Raft Turns Turtle In Chenab River In Reasi, All 13 Rescued

JAMMU, May 8: A raft carrying 13 people turned...

JKDMA Issues Avalanche Alert for Four Districts

SRINAGAR: Jammu and Kashmir Disaster Management Authority (JKDMA) on Monday...